Opinions of the State Grid on promoting the grid connected management of distributed power sources (Revised Edition)
author: comefrom: date:2017-6-15 16:27:32 hits:138

One. General Provisions  

1., in order to further implement the company's "four services" requirements, to promote the accelerated development of distributed power supply, improve the distributed power grid management and improve the level of grid services, formulate this opinion.

2., the opinions in the "national Power Grid Corp on the distribution of power grid services work" on the basis of clear distribution power grid connected to the whole process of management responsibilities, processes, convergence and work requirements.

3. the relevant units of the state Power Grid Corp shall carry out relevant work in accordance with the present opinions.

Two, scope of application

The 4. opinion refers to distributed power, refers to the user is located near the construction site or installation, operation mode to the user side spontaneously occupied mainly excess electricity access, energy cascade power generation facilities and distribution network system in the balance of regulation or power output by multi cogeneration facilities. Including solar energy, natural gas, biomass energy, wind energy, geothermal energy, marine energy, resources, comprehensive utilization, power generation (including coal mines, gas, power generation), etc..

5., this advice applies to the following two types of distributed power supplies (excluding small hydro power):

First class: 10 thousand volt and below voltage level access, and single and network outlets, the total installed capacity of not more than 6 MW of distributed power supply.

Second class: 35 thousand volt level access, years of spontaneous distributed power power consumption of more than 50%; or 10 thousand volt level access and single point total installed capacity of more than 6 MW, years of spontaneous distributed power supply power consumption of more than 50%.

6. access points for public connection point (Annex 1), power generation projects, all Internet small hydropower, distributed power projects in addition to first, second outside, in a simple and efficient principle to grid services, implementing the relevant provisions on the management of conventional power supply.

Three, access applications accepted 

7., city or county company marketing department (customer service center) is responsible for accepting the distributed power supply (attachment 2) access application, to assist the project owner to fill in the access application form (attachment 3), to receive relevant supporting documents and information.

8., the city's marketing department (customer service center) is responsible for archiving access applications, reported to the city Department of corporate development. To the city's development department notified by the Institute (Municipality for the Research Institute, the same below) for access system. The working time limit is 2 working days.

Four, access system program determined 

9., the Institute is responsible for formulating access system. The content of the access system is carried out in depth according to the requirements of the state and the company (Appendix 4), and reference to the typical design of the distributed power supply access system. There are 30 types of work time limit, the first is the distributed photovoltaic power generation single point grid connected project, 10 working days, the multi-point grid connected project is 20 days, and the second type of project is 50 working days.

10. city company marketing department (customer service center) is responsible for organizing relevant departments to verify the 380 volt access project access system program, issued comments. The working time limit is 5 working days.

The development of 11. municipal departments responsible for organizing the examination of 35 thousand volts and 10 thousand volts (access project for multiple grid projects, at least one point is 35 thousand volt and 10 thousand volt access) access system, issued by the review opinions and the network opinion letter. The working time limit is 5 working days.

12. city or county company sales department (customer service center) is responsible for the access system scheme of 380 volt access project confirmation (Annex 5), the scheme of access system of 35 thousand volts or 10 thousand volts, access project confirmation (Annex 5), access network opinion letter (Annex 6) to inform the project owners, working time 3 working days. Responsible for receiving and arranging access system proposal consultation.

13.380 volt access project, the project owner confirmed the access system program, the marketing department will be responsible for the access system program confirmation in a timely manner to the city, the company development department, finance department, the Department of transportation and inspection. The project owner shall carry out project approval (or filing) and project construction in accordance with the approved access system program.

14 thousand and 350 V, 10 thousand V access project, the project owner to confirm the scheme of access system, the development of company will be responsible for the scheme of access system confirmation, access to the grid the letter of advice, timely copy to the city's financial department, inspection department, sales department, control center, ICT company, and the record company submitted to the provincial development department. The project owner shall carry out the project approval (or filing) and engineering design according to the letter of recommendation for access to the power grid.

15., the company provides project filing services for natural person distributed photovoltaic power generation projects. For distributed photovoltaic power generation project and its own residential residential area construction by natural persons, the development of city, the company received the confirmation after the project access system, according to the administrative measures for the filing of local departments in charge of energy projects, the monthly concentrated natural person project project owner filed to the administrative department of energy of the local financial department for the record, a copy of the documents to the city company.

Five , access system engineering construction

16. city (county) company is responsible for public power grid reconstruction project (including communication cable installed with public power network line and corresponding public power grid, substation, communication equipment transformation, etc.).

17., the company for the public power grid reconstruction project to open up a green channel (Annex 7).

18 thousand and 350 V, 10 thousand V access project, the project owners in the project approval (or record), before construction of the access system, access system engineering design related data (Annex 8) submitted to the city or county level company sales department (customer service center). The city's sales department (customer service center) is responsible for the access system engineering design related data archive, organization development department, inspection department, transport control center and other departments (units) to review the access system engineering design, issued a reply (Annex 9) and inform the owner of the project and a copy sent to the control center, the work time is 10 working day. The project owner shall carry out follow-up work on the access system construction according to the reply opinions. If the review fails, propose a modification plan.

Six, grid acceptance and debugging

19. city or county company sales department (customer service center) is responsible for handling the project owners and network acceptance and grid application debugging, assist the project owner to fill in the grid and grid application debugging and acceptance (Annex 10), receiving relevant information (Annex 11).

20., the city's marketing department (customer service center) is responsible for network acceptance and grid debugging, application information archiving, and reported to the city's corporate finance department, regulatory center, the Department of transportation and inspection. The working time limit is 2 working days.

21. after acceptance of the grid connection and commissioning, the local marketing department (customer service center) is responsible for installing the gateway metering and power generation metering device. The working time limit is 8 working days.

22. network acceptance and grid debugging the admissibility of the application, the 380 volt access project, the municipal company sales department (customer service center) is responsible for the project owners (or power users) on the purchase and sale of electricity, power supply and scheduling aspects of the contract work, the signing of the contract, financial Department, CC company control center, the provincial the trading center for the record company. 35 thousand V, 10 thousand V access project, the sale of electricity purchase contracts and scheduling protocol synchronization signed to the city's sales department (customer service center) taking control center to determine the date of signing, the municipal company sales department (customer service center) is responsible for the project owners (or power users) on the purchase and sale of electricity and power supply area the signing of the contract, the contract copy to the city's financial department signed the provincial company, the trading center for the record, to the city's control center responsible for dealing with project owners (or power users) on the signing of the scheduling protocol. The working time limit is 8 working days.

23. of the electric energy metering device installation, contract and agreement signed after the 380 volt access project, the municipal company sales department (customer service center) is responsible for organizing relevant departments to carry out the project approval issued by the grid and grid debugging, network acceptance opinion (Annex 12), grid connected directly into the grid through debugging. 35 thousand V, 10 thousand V access project, to the city's control center is responsible for organizing relevant departments to carry out grid project acceptance work, issued by the network acceptance opinions (Annex 12), to carry out the grid debugging work, through debugging directly into the grid. If acceptance or debugging is not up to standard, propose corrective action plan. The working time limit is 10 working days.

24. distributed power supply network equipment should be in accordance with the grid scheduling agreement, into the city, the company's regulatory center, scheduling management. The switching operation of the distributed power supply and the network switch (belonging to the user's assets) must be confirmed by the local company and the project staff, and approved by the relevant departments of the local company. Among them, 35 thousand volts and 10 thousand volts access project, by the city company control center confirmation and approval; 380 volt access project by the city company marketing department (customer service center) to confirm and permit.

Seven, the state subsidy fund management

In September 30th 25. annual financial departments at city or county level shall be responsible for the company before the annual underground renewable energy subsidies to fund the annual budget submitted to the provincial finance department of the company. In the company's financial department after the audit summary in October 10th of each year before the financial department at the headquarters.

26. the Finance Department of the head office of the company is responsible for the grant of the grant funds to the Ministry of Finance in accordance with the requirements of the Ministry of finance, and shall promptly pay the subsidy to the provincial company after receiving the grant of the grant from the Ministry of finance. After receiving the funds, the Finance Department of the province will make timely payments to the municipal or county level companies. The financial department of the city, county or county level shall be responsible for paying the subsidy to the project owner (or the electricity user) in time after receiving the grant funds.

Eight, grid connected information management

27. Development Division (Office of new energy and distributed power supply leading group) is responsible for centralized management of distributed power grid connected information (Appendix 13).

Nine, grid consulting services

28. Sales Department (customer service center) is responsible for the distributed power grid services (Annex 14) centralized management, provide grid consulting services include 95598 service hotline, online business hall, city and County company sales department (customer service center).

2-1.jpg

2-2.jpg

2-3.jpg

2-4.jpg

2-5.jpg

2-6.jpg

2-7.jpg

3-1.jpg

3-2.jpg

3-3.jpg

3-4.jpg

3-5.jpg

4-1.jpg

4-2.jpg

4-3.jpg

4-4.jpg

4-5.jpg

4-6.jpg




AmensoLar
About/Culture
Enterprise Qualification/Partner
News/Latest activities
Contact us
TEL:0512-66327066
Email:sales@amensolar.com